SINTERING PROCESS OF LOW CEMENT CASTABLE
1. To prevent the refractory lining from freezing, ambient temperature must above 5℃ at any time, especially for unsintered refractory lining.
2. Maintain in natural condition for 72hrs before sintering
3. At preliminary stage of sinterirng (before 340℃) , use extra heater,do not use burner of reverb furnace to avoid partially over heating .
4. Take into account the maximum temperature as reference, thermocouple should not close to heater, temperature deviation of each thermocouple should less than 100℃ during each holding stage, otherwise, prolong the holding time.
5. Stop increase temperature when steam exists, holding until steam disappear, then continue the sintering.
6. Put into melting directly after sintering,do not shut down frequently to avoid cracks. When reach the working temperature, keep it for at least one month in order to release thermal stress.
7. When needs to empty the furnace, make sure the cooling speed less than 50℃/hr, open the door till temperature below 100℃. Follow cold start technology, charge aluminum after holding process( 740℃).
 
A
We could not find any corresponding parameters, please add them to the properties table
ewm
WeChat public account
ewm
View mobile website

Contact Us

Address : No. 99, Yiqing Road, Gaozi Street, EconomicDevelopment Zone, Dantu District, Zhenjiang City

Fax : +86-511-85683066
E-mail :
sales@sfr168.com   
Website :
http://www.sfr168.com
Copyright © 2021 Sino-Foundry Refractory(Jiangsu) Co.,Ltd. All Rights Reserved. 苏ICP备19058941号-1 Powered by:www.300.cn Changzhou
返回顶部
搜索
Search